May 4 through May 11, 2017

>>See PDF of the construction map

- WORK AREA "A"- Science & Engineering Courtyard (North)

>Thursday: Place geotextile fabric and 6-inches of compacted sub-base/ Establish survey points for "NEW EDITION"- Potential Minor Vibration & Noise

> Friday: Continue survey points for "NEW EDITION"; Start excavation next to foundations of towers 1,2, & 3.- Potential Minor Vibration & Noise

> Monday: Continue excavation next to foundations of towers 1,2, & 3.- Potential Minor Vibration & Noise

> Tuesday: Layout concrete removal on existing columns (North side of S&E)

> Wednesday: Remove concrete from existing columns- Vibration & Noise to adjacent classrooms North side of S&E

WORK AREA "B"- South side of Science & Engineering

> Friday; Relocate existing condenser units- Coordinate with facility IT department during operation

> Monday; Remove existing tree (morning) & begin utility relocations SW corner of S&E.- Relocate students/faculty to new asphalt walkway during operations

> Tuesday; Continue utility relocations SW corner of S&E.- Relocate students/faculty to new asphalt walkway during operations

> Wednesday; Continue utility relocations SW corner S&E.- Relocate students/faculty to new asphalt walkway during operations

WORK AREA "C"- Alexander lane

> Thursday through Monday; Increased truck traffic due to deliveries - Flag persons provided during deliveries, North lift gate on Alexander Lane open 7am-3pm

WORK AREA "D"- Contractor break Area

> Friday; Install temporary fence & gates

WORK AREA "E"- Contractor Material Lay-down Area

> Thursday; Remove curb, box out & asphalt paving to widen entrance at Alexander Drive- Flag-persons provided at each portion of each portion of intersection